March Construction Update

The construction of Art House is moving rapidly towards completion.

We are pleased to report that the Art House roof slab at level 27 has been poured and the tower structure is now "topped out".

With windows now installed to level 25 and exterior painting having commenced in February, the unique facade which is Art House is really beginning to shine. Internally our apartments are substantially complete up to level 12, with interior fit out works in progress working through the upper levels.

In regards to the building construction status, we are still on track to welcome the first residents from mid-2017.

View the latest progress video of Art House.